Private Development Projects

Link to Private Development Permit Application

For more information about the projects listed below, please contact:

Private Development Program Manager at 503-722-5500

Project Details Current Status

Estimated Project

Completion Date

Tanner Springs Parcel B Construction plan review is complete. December 2016
Lort Partition

Public Improvement Engineering Plan Review and Construction Permit are approved.

Construction contingent on contractor's schedule

April 2016
Shady Hollow Village

Curb and sidewalk have been poured.

Contractor wrapping up punchlist

January 2016

Lake Oswego Tigard Water Treatment Plant

Transmission Line

Partnership is installing pipeline in right-of-way along Mapleton.

Work zone expected to progress 50-100 feet per day depending on conditions 

2016

Lake Oswego-Tigard

Water Treatment Plant

Curb has been installed on Kenthorpe Way and Mapleton Drive.  Sidewalk has been installed at the end of Kenthorpe Way.

2016
     

 

Completed Projects

 
Weatherhill Subdivision Plat signed and released to Clackamas County Complete
Suncrest Partition Plat signed and released to Clackamas County Complete
Stoneking Subdivision Plat signed and released to Clackamas County Complete
Harper Subdivision Plat signed and recorded with Clackamas County Complete
Renaissance at Willamette Plat signed and recorded with Clackamas County Complete
6th Ave Partition Plat signed and recorded with Clackamas County Complete
Rosemont Subdivision

Completed all Public Improvements

Plat approved and released to County

Complete
Sunbreak Subdivision

Completed all Public Improvements

Plat approved and released to County

Complete
Police Station New building is occupied and open to the public Complete
Benjamin Heights Partition

Final Plat has been approved and released to Clackamas County for recording

Complete
Santa Anita Partition

Completed all Public Improvements

Final Plat approved and released to Clackamas County

Complete
Dollar Street Partition

Final Plat recorded with the County

Complete
Falcon Place Subdivision

Final Plat recorded with the County

Performance Bond in place

Complete

West Linn High School

Parking Reconfiguration

Maintenance Bond in place through 02/03/2015 Complete