22870 S. Weatherhill Subdivision
General public improvements (storm, sewer, water, streets) associated with new 12-lot subdivision.
Planning Department File
Status Updates
7/23/2024- Paving of Weatherhill expected 8/7-9.
4/29/2024- Work in closeout phase.
10/10/2023- Paving to begin the week of 10/16.
7/20/2023- Work to install new utilities ongoing. Repairs to damaged sidewalks.
6/13/2023- Hillside grading and compacting work.
5/15/2023- Sanitary sewer installed onsite.
5/1/2023- Private storm sewer installation ongoing.
3/27/2023- Sanitary Sewer installed to Crestview.
3/1/2023- Work began to clear brush for access to install storm and sanitary sewer infrastructure.
12/8/2022- Work ongoing.
10/14/2022 - Grading revision approved.
2/17/2022 - Contractor continues to import soil for Satar Street right of way.
1/18/2022 - Construction is underway. Erosion control measures in place.
11/22/2021 - Final construction plans approved. Construction is planned to commence after the 1st of the year.
Disclaimer
Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.