Broadway Street Improvements

Project ID: 
PI-19-02
Project Type:
Private Development Project (Public Improvement)
Project Status: 
In Process
Project Budget: 
NA
Project Manager: 
Clark Ide
Project Contact Information: 
cide@westlinnoregon.gov 503-722-3437
5779 Broadway Street
West Linn, OR 97068
Neighborhood: 
Bolton

Half-street improvements adjacent to 5779 Broadway Street.  The City will be partnering with this development to extend street improvements to Webb Street.

 

Planning Department File:

MISC-20-02

 

Status Updates

10/09/2023- Public improvements substantially complete.

8/28/2023- Curbs being installed to the Webb St. intersection. 

6/27/2023- Sanitary sewer laterals are being installed.

6/8/2023- Storm sewer work continues. 

5/5/2023- Storm sewer work including the installation of a new manhole has begun.

4/22/2023- Utility work starting with PGE expected to begin 5/1.

2/7/2023 - Due to Developer-driven design changes, construction plans for street improvements are back in review pending approval prior to work continuing. 

9/13/2022 - Design and contract negotiations continue.

01/21/2022 - Design of public storm sewer is being re-evaluated to accommodate additional street improvements and new sidewalk. Construction in  the right-of-way will continue early 2023. 

09/23/2021 - Sewer laterals installed.  Material supply issues have stalled progress.  Work anticipated to commence again in the coming weeks.

01/19/2021 - Work in the right-of-way commencing.

10/22/2020 - Construction drawings approved.  Pre-construction meeting held.

03/06/2020 - Awaiting submittal of revised construction drawings.

11/27/2019 - Construction plans submitted for 1st review and comments provided back to developer.

6/6/2019 - Public Improvement Permit fees were paid and permit was issued to the developer. 

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.