Design for upgrading Calaroga sanitary sewer pump station and improving maintenance access.

Status Updates

8/1/2023- Land Use process is underway. Consultant is preparing 90% design deliverable. 

6/29/2023- Presentation to Robinwood Neighborhood Association scheduled for July 11th.

5/1/2023- 30% deliverable under review.

1/27/2023- Field investigation complete. Preparation of land use application materials and 30% design is underway.

1/23-24/2023- Geotechnical investigation via drilling. 

1/17/2023- Surveying of site.

Files:

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.