Broadway Street Improvements
Half-street improvements adjacent to 5779 Broadway Street. The City will be partnering with this development to extend street improvements to Webb Street.
Planning Department File:
Status Updates
10/09/2023- Public improvements substantially complete.
8/28/2023- Curbs being installed to the Webb St. intersection.
6/27/2023- Sanitary sewer laterals are being installed.
6/8/2023- Storm sewer work continues.
5/5/2023- Storm sewer work including the installation of a new manhole has begun.
4/22/2023- Utility work starting with PGE expected to begin 5/1.
2/7/2023 - Due to Developer-driven design changes, construction plans for street improvements are back in review pending approval prior to work continuing.
9/13/2022 - Design and contract negotiations continue.
01/21/2022 - Design of public storm sewer is being re-evaluated to accommodate additional street improvements and new sidewalk. Construction in the right-of-way will continue early 2023.
09/23/2021 - Sewer laterals installed. Material supply issues have stalled progress. Work anticipated to commence again in the coming weeks.
01/19/2021 - Work in the right-of-way commencing.
10/22/2020 - Construction drawings approved. Pre-construction meeting held.
03/06/2020 - Awaiting submittal of revised construction drawings.
11/27/2019 - Construction plans submitted for 1st review and comments provided back to developer.
6/6/2019 - Public Improvement Permit fees were paid and permit was issued to the developer.
Disclaimer
Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.