South Fork 24-inch Pipe Restraint

Project ID: 
PW-18-01
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
Complete
Project Budget: 
TBD
Project Manager: 
Erich Lais
Project Contact Information: 
Erich Lais 503-722-3434 elais@westlinnoregon.gov
Submission Date: 
12/19/2017
Deadline Date: 
07/09/2018

Restrain existing unrestrained pipe joints on a 24-inch diameter steel water transmission main located on a steep slope above Abernathy Creek in Oregon City.

Status Updates

01/08/2019 - Project complete. 

11/14/2018 - Waiting on delivery of 24-inch valves. All but one joint has been restrained on the hillside. Final one will be welded during shutdown of valve installation.

10/10/2018 -  5 joints have been exposed and welded. 3 more joints are planned to be exposed and welded this week. 24 inch valves are expected by the end of the month.

09/12/2018 - Work has begun on the project.

08/08/2018 - Project has been awarded. Pre-construction meeting held on 8/1. Shutdown still tentatively planned for 9/4.

06/05/2018 - Pre-bid meeting to be held on 06/12/2018. Complete bids are due 06/21.

Disclaimer

Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.