Tualatin Valley Fire & Rescue Station #55
Status Updates
12/05/2018 - Project is complete and occupancy has been granted.
11/13/2018 - Project closeout is ongoing.
10/09/2018 - The Fire District's contractor/engineer continues to work on final punch list items.
09/12/2018 - The project is substantially complete and a Temporary Certificate of Occupancy has been issued. The contractor/engineer is working on final punchlist items.
08/08/2018 - Project is substantially complete. The Fire District's contractor is working on final punchlist items.
06/11/2018 - Frontage improvement work is ongoing.
04/09/2018 - Onsite construction continues.
03/05/2018 - Onsite construction continues
12/18/2017 - Onsite construction continues.
10/23/2017 - Onsite construction continues.
08/31/2017 - Onsite construction continues. Minor work in the right-of-way occurring for installation of power. Street improvements are anticipated to begin in spring of 2018.
6/07/2017 - Onsite construction underway. Applicant must provide performance bond prior to beginning public improvements.
05/22/2017 - Erosion control measures in place
02/23/2017 - Public Improvement Permit issued
Disclaimer
Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.