Tanner Ridge at Rosemont
Planned 50-lot subdivision including storm and street improvements. This project includes a DEQ 1200C erosion control permit.
Associated Planning Department Files:
Status Updates
11/14/2018 - Project is complete and closed out.
10/10/2018 - Project is substantially complete. Landscape restoration and planting remains.
08/08/2018 - 9 building permits have been issued so far for new home construction.
06/05/2018 - Plat recorded, building plans in for review.
04/09/2018 - Contractor wrapping up punchlist items prior to final plat approval.
03/05/2018 - Contractor is working on punchlist items for onsite construction.
12/18/2017 - Onsite paving is complete. Contractor plans to transition into the offsite improvements for Rosemont and Parker.
11/02/2017 - Streets are installed. City testing and acceptance of public utilities is pending.
08/31/2017 - Construction is underway and sanitary sewer is being installed. Offsite improvements (Rosemont Rd. and Parker Rd.) are currently under design review.
07/26/2017 - Initial erosion control inspection performed with corrections issued to repair torn sediment fence and add sediment fence along buffer approach to tree protection area.
07/05/2017 - DEQ 1200C Erosion Control Permit issued.
06/22/2017 - Public Improvement Permit issued; Performance bond required prior to start of construction.
Disclaimer
Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.