Pimlico Drive Sidewalk Ramp Replacement Project

Project ID: 
PW-18-07
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
Complete
Project Budget: 
$32,100
Project Manager: 
Morgan Palmer
Project Contact Information: 
Morgan Palmer- Associate Engineer mpalmer@westlinnoregon.gov 503-722-3436
Submission Date: 
11/08/2018
Project Dates: 
12/01/2018-01/31/2019
Neighborhood: 
Hidden Springs

This project includes installing sidewalk ramps along Pimlico Drive between Palomino Circle and Club House Circle. The existing curb reduces mobility options for residents along Pimlico Drive, specifically when trying to cross the street at intersections. A total of twelve new curb ramps will be installed.

This is a sketch of an added curb ramp on Pimlico Drive at Palomino Way.
This is a sketch of an added curb ramp on Pimlico Drive at Palomino Circle.
This is a sketch of an added curb ramp on Pimlico Drive and Club House Circle.
Status Updates

4/30/19 - Project is complete. Contractor completed constructing all ramps and restored landscaping around ramps. City staff measured slopes for all ramps and posted results.

4/10/19 - Contractor has completed constructing all ramps. However, we will be reworking several ramps based on feedback from City staff and neighbors to improve the finish and slopes. The ramps will be reworked this week.

3/11/19 - Contractor has started work by removing concrete sidewalks and forming up new ramps.

02/27/19 - The City entered into a contract with 4-Belt Concrete and Masonry to complete the work by April 30, 2019.

01/08/19 - A contractor has been selected. City is negotiating the contract and selecting a start date for work.

11/13/18 - The project was advertised on the City's bid website as a "Request for Quotes". This intermediate procurement period ends on 11/30/2018.

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.