2017 Road Program

Project ID: 
PW-17-01
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
Complete
Project Budget: 
$852.181.00
Project Manager: 
Erich Lais
Project Contact Information: 
Erich Lais elais@westlinnoregon.gov 503-722-3434
Project Dates: 
8/22/2017 - 90 Day contract
Public Notice Deadline: 
Not Applicable
Neighborhood: 
Robinwood

This street improvement project generally includes asphalt pavement removal and replacement, cement treated subgrade, and storm sewer improvements.

Status Updates

12/14/2017 - Final remaining concrete driveways poured. Project is complete.

11/02/2017 - Construction is complete. Kenthorpe Way and Mapleton Drive have been paved. City has placed rock along road shoulders.

09/23/2017 - Mapleton Drive has been topped with 2-inches of new asphalt.  Driveways are pending completion and are tentatively scheduled for the week of 9/25 (weather dependent).  Pulverizing began 9/21/2017 on the east end of Kenthorpe.  Grading and reshaping will continue through the week of 9/25/2017 (completion anticipated mid-week).

08/31/2017 - Project underway, contractor is performing driveway prep and stormwater improvements.

08/23/2017 - Second Kenthorpe Way Paving Open House held at Robinwood Station

08/16/2017 - Notice to proceed issued for August 22nd.

08/02/2017 - Second Kenthorpe Way Paving Open House (canceled and rescheduled due to excessive heat)

07/10/2017 - Contract awarded to S-2 Contractors

06/29/2017 - Kenthorpe Way Paving open house at Robinwood Station

06/21/2017 - Bid Opening with S-2 Contractors as the lowest responsive bidder

05/24/2017 - Advertisement for Bid

Disclaimer

Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.