Status Updates
01/14/2016 - Acceptance of public improvements issued. Project closed.
12/02/2015 - Curb and sidewalks have been poured. Contractor is working on final punch list and awaiting City's final acceptance of public improvements.
10/05/2015 - Sidewalk and ADA ramp forms inspected and approved. Concrete sidewalks poured in section along Highway 43 frontage.
09/03/2015 - Prepping for paving, saw cutting paving limits and connection points; locating and raising structures. Water Department to adjust meter to parks property. Contractor to backfill and compact.
07/20/2015 - Working on onsite Contech storm detention system. Excavated and placed large diameter corrugated pipe tanks in services and plumbing to storm main and flood control manhole.
05/28/2015 - Grading activities on Highway 43 frontage. Formed up headwall at storm outfall and poured concrete after forms were approved by the City.
05/13/2015 - Water department shut down service for abandonment of 2 services on Willamette Dr. New sanitary sewer manhole installed on Shady Hollow Way; installed lateral from Shady Hollow Village to new manhole.
04/13/2015 - Permits are approved and construction is underway.
09/18/2014 - Public Improvement engineering plan and construction permit under review.
09/03/2014 - Public Improvement Permit issued.
Disclaimer
Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.