Savannah Heights Subdivision

Project ID: 
PI-16-02
Project Type:
Private Development Project (Public Improvement)
Project Status: 
Complete
Project Manager: 
Erich Lais
Project Contact Information: 
Erich Lais elais@westlinnoregon.gov 503-722-3434
Project Dates: 
04/05/2016 - Accepted Public Improvement Permit
Deadline Type: 
none
Neighborhood: 
Savanna Oaks

This project is a 6-lot subdivision with public improvements.

Developer: Bland Circle Estates, LLC

Associated Planning Department Files:

SUB-15-02

Status Updates

10/10/2018 - Project is complete.

09/12/2018 - Plat approved, fees are payed.

08/08/2018 - Plat has been approved.

06/05/2018 - Improvements complete, waiting for developers to pay final fees.

04/09/2018 - Developers working towards completing punch list, items include SDC fees.

03/05/2018 - Property has changed owners since construction began. New owner has been provided with remaining punchlist items for completion.

12/18/2017 - Public Improvements have been accepted. City is waiting on maintenance bond prior to project closure.

11/02/2017 - Project is in process of close out. Contractor is working on punch list.

08/31/2017 - Utility infrastructure is installed; curb and gutter is completed. Paving to be scheduled once PGE conduit installation is complete.

06/26/2017 - City staff met with contractor on site to review ADA ramp requirements.

06/05/2017 - Excavating trench for conduits to street lights fronting Bland Circle.

04/12/2017 - Installation of 12' PVC storm main

04/06/2017 - Installation of storm laterals has begun.

03/20/2017 - Temporary access to Bland Circle Reservoir installed off Sunbreak Ln. Proof rolls on Tannler Dr. completed and inspected.

03/07/2017 - Excavation of pond/swale has begun and requires use of rock hammer due to rock soil conditions.

02/28/2017 - Demolition/tree removal and clearing of fallen trees. Phase 1 of erosion control partially installed. Inlet protection in place.

07/20/2016 - Construction plan review completed. Developer to submit performance bond before construction can begin.

04/05/2016 - Public Improvement application accepted

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.