Lake Oswego Emergency Intertie Pump Station

Project ID: 
PW-14-12
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
Complete
Project Budget: 
$230,400.00
Project Manager: 
Erich Lais
Project Contact Information: 
Erich Lais elais@westlinnoregon.gov 503-722-3434
Project Dates: 
02/23/2015 - 05/25/2015
Public Notice Deadline: 
05/05/2015 - 07/04/2015
Deadline Type: 
none
Neighborhood: 
Robinwood

Project includes the installation of one end suction centrifugal pump, piping, valves, and electrical and control system
upgrades within the existing Emergency Intertie Water Pump Station. Exterior site improvements include yard fencing,
piping and the installation of a buried flow meter vault.
 

Status Updates

04/27/2016 - Reimbursement from City of Lake Oswego received for LO portion of design and project management services per Article V.C.2(a) of the Cooperative Agreement of Joint Funding of Water System Improvements.

03/23/2016 - Project completed

12/03/2015 - Pump installed, contractor waiting on electrician to verify circuitry.

09/25/2015 - Contractor waiting on pump shipment; valve installation complete.

05/05/2015 - Notice to proceed issued

04/13/2015 - Contract awarded by Council to Cascade Water Works (lowest responsive bidder)

03/31/2015 - Bid opening (5 bid received)

03/05/2015 - Advertisement for Bid published

Disclaimer

Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.