2019 Pavement Repair Project

Project ID: 
PW-18-09
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
Complete
Project Budget: 
$100,000
Project Manager: 
Erich Lais
Project Contact Information: 
elais@westlinnoregon.gov 503-722-3434

Pavement repair in various areas of the City. 

Status Updates

5/06/2019 - All work complete

5/02/2019 - Repair areas on Summit @ Apollo completed. Repairs at Athena, Artermis, and Horton began.

4/16/2019 - Areas for pavement repair were sawcut.

Files:
PDF icon Contract (12 MB)
PDF icon Bid Maps (12 MB)

Disclaimer

Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.