2017 Waterline Project
This waterline replacement project generally consists of installing 3,600 linear feet of 8-inch ductile iron water line and 1,300 linear feet of 12-inch ductile iron water line. Permanent trench paving, hydrant installation, water service connections, surveying, and landscape restoration are also included.
Status Updates
09/20/2017 - Project complete. Punch list items complete. Restoration for staging area at Robinwood Station is finished.
08/31/2017 - Project is being closed out. Contractor will be wrapping up punch list items within the next week.
08/02/2017 - Construction wrapping up, equipment being removed from staging areas, site restoration taking place
07/19/2017 - Approved chlorination test
07/18/2017 - Approved pressure test
06/29/2017 - Installation of 1" water services on Kenthorpe. Excavation, pipework and backfilling taking place. All services to be installed by end of month.
05/23/2017 - 482 linear feet of 12" ductile iron installed on Old River and approximately 235 linear feet of 8" ductile iron installed on Kenthorpe Way.
05/01/2017-05/04/2017 - Tie into existing 10' ductile iron pipe on Hillcrest; install last 72 linear feet of 12" ductile iron going south toward Ridgebrook Dr. tie in location. Installation of 1" water services.
04/24/2017 - Installation of approximately 420 ft of 8" ductile iron water main on Valley View
04/17/2017 - Notice to Proceed
02/22/2017 - Notice of Award issued
02/13/2017 - Contract awarded to Oregon Underground Inc.
01/19/2017 - Project advertised for bid
Disclaimer
Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.