2016 Sanitary Sewer Rehabilitation (CIPP) Phase 6

Project ID: 
PW-15-06
Project Type:
City Initiated Project (Capital Improvement)
Project Status: 
Complete
Project Budget: 
$991,640.40
Project Manager: 
Erich Lais
Project Contact Information: 
Erich Lais elais@westlinnoregon.gov 503-722-3434
Project Dates: 
04/25/2016 - 07/24/2016
Deadline Type: 
none

Project consists of cleaning, cctv and CIPP (cured in place pipe) of approximately 26,000 linear feet of sanitary sewer pipe in various locations throughout the City.

Status Updates

12/01/2016 - Project completed with all punchlist items complete.

08/26/2016 - Cleaning of 24" storm pipe and removal of defects. Inspection and cleaning of laterals.

07/21/2016 - Approximately 8,000 linear feet of pipe cleaned and lined.

06/22/2016 - Traffic control measures inspected

04/25/2016 - Construction start date

03/14/2016 - Contracted awarded by Council to Insituform Technologies (lowest responsive bidder)

02/24/2016 - Bid Opening (2 bids received)

01/28/2016 - Advertisement for Bid published

Disclaimer

Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.