Sahallie Illahee Park

Project ID: 
BD1807
Project Type:
Parks
Project Status: 
Complete
Project Budget: 
$90,000 Bond Allocation $62,500 funded by State Parks Grant
Project Manager: 
Megan Big John
Project Contact Information: 
mbigjohn@westlinnoregon.gov, 503-742-6047
Project Dates: 
July 2018-June 2019
Sahallie Ilahee Park
4300 Horton Road
West Linn, OR 97068

Work at Sahallie Illahee Park will consist of better ADA access and a new nature based playground and the demolition and re-construction of the Horton Road basketball court.
 

Project Cost = $100,009 ( Oregon Parks & Recreation Department funded additional  $62,500  for the project)

Project Completed - 2020

Nature play area
New basketball court and hoop
New swing

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.