Sunset Fire Hall

Project ID: 
BD1823
Project Type:
City Facilities
Project Status: 
In Process
Project Budget: 
$100,000 Bond Allocation
Project Manager: 
Megan Big John
Project Contact Information: 
mbigjohn@westlinnoregon.gov, 503-742-6047
Sunset Fire Hall
2215 Long Street
West Linn, OR 97068

Project includes exterior painting, park connectivity (upgrades to parking lot and ADA transitions to the park), restroom and kitchen upgrades.

Project cost to date = $151,383

Required Fire Suppression Sprinklers (unexpected requirement)- Completed 12/7/2021

Interior ADA Upgrades - Delayed 
ADA evaluation revealed the need to re-classify facility and add required Fire Suppression system.

Park Connectivity - Completed 7/18/2020

Exterior Facility Painting - Completed 6/11/2019
 

 

Sunset Firehall repainted
Sunset Firehall front of building photo
New improved parking lot
Park connectivity, bollard system and Library book drop

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.