Sunburst Park

Project ID: 
BD1815
Project Type:
Parks
Project Status: 
Complete
Project Budget: 
$80,000 Bond Allocation
Project Manager: 
Megan Big John
Project Contact Information: 
mbigjohn@westlinnoregon.gov, 503-742-6047
Project Dates: 
July 2019 - June 2020
Sunburst Park
19900 Derby
West Linn, OR 97068

Improvements to Sunburst Park include a pavement overlay to the internal pathway and leveling and surfacing the basketball court with a conversion to an adjustable height backboard and rim.

Project Cost = $74,004

New Asphalt pathways in park  - Completed 7/2020

New adjustable basketball hoop installed - Completed 3/30/2020

New asphalt overlay on Basketball court - Completed 
 

 

New Asphalt pathway

Disclaimer

Disclaimer notice regarding the project information on this site: The City of West Linn is pleased to provide as much information as possible on our website for the benefit of the public. This information is updated by staff on a periodic (not daily) basis. However, please be aware of the following: The information on this site is not the official file of record and there may be additional project information in the file of record that is not posted on this site. The information on this site may not include the latest submittals or changes to an application. Interested parties are encouraged to call the City project manager with any inquiries on a project. The official file of record is kept in the City Department managing the project and is available for public review during regular office hours at City Hall located at 22500 Salamo Road, West Linn, Or 97068. Any questions related to any project should be directed to the project manager listed in the file, or by calling City Hall at 503-657-0331.