Project ID:
BD1813
Project Type:
Parks
Project Status:
Complete
Project Budget:
$10,000 Bond Allocation
Project Manager:
Megan Big John
Project Contact Information:
mbigjohn@westlinnoregon.gov, 503-742-6047
Project Dates:
July 2019 - June 2020
Robinwood Park
3600 Fairview Way
West Linn,
OR
97068
See map: Google Maps
Improved drainage and detention wall around the basketball court due to water/dirt flowing on the court.
Project Cost = $18,699
Project Completed - 10/2020
Disclaimer
Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.