Bolton Fire Hall
Project description and funding allocation will follow future City Council discussion and direction as the future of the building is determined.
Project Cost to date = $15,803
Assessment Associates Inc. completes Environmental Site Assessment & Asbestos/Lead-Based Paint Survey (hazard materials study) - Completed 6/24/2020
3 Kings contracted to remove and decommission Heating Oil Tank located onsite and monitoring continues - Completed 1/27/2020
Concrete GPR LLC conducts screening of tank discovered onsite - Completed10/25/2029
Disclaimer
Disclaimer notice regarding project information on this site: While every effort is made to keep project information current and accurate, the City does not guarantee the completeness, reliability, or accuracy of the information and assumes no responsibility for any errors, omissions, or discrepancies.