You are here

Private Development Projects

Link to Private Development Permit Application

For more information about the projects listed below, please contact:

Private Development Program Manager at 503-722-5500

Project Details Current Status

Estimated Project

Completion Date

Shady Hollow Village Public Improvement Engineering Plan and Construction Permit under review March 2015
6th Ave Partition Public Improvement Engineering Plan and Construction Permit under review December 2014
Renaissance at Willamette

Public Improvement Engineering Plan and Construction Permit approved

Erosion control in place and construction under way

November 2014
Suncrest Partition Public Improvement Engineering Plan and Construction Permit under review December 2014
Harper Subdivision

Erosion control is in place

Grading and construction is under way

Fall 2014
Weatherhill Subdivision

Public Improvement Engineering Plan and Construction Permit is approved

Construction is under way

2014
Sunbreak Subdivision

Final Plat has been approved and released to Clackamas County

Fall 2014
Rosemont Subdivision Final Plat has been approved and released to Clackamas County Fall 2014

Lake Oswego Tigard Water Treatment Plant

Transmission Line

Engineering and Construction Permit is complete

2016

Lake Oswego-Tigard

Water Treatment Plant

Under Construction

Coordinating with erosion control inspectors for regular visits

2016
     

 

Completed Projects

 
Police Station New building is occupied and open to the public Complete
Benjamin Heights Partition

Final Plat has been approved and released to Clackamas County for recording

Complete
Santa Anita Partition

Completed all Public Improvements

Final Plat approved and released to Clackamas County

Complete
Dollar Street Partition

Final Plat recorded with the County

Complete
Falcon Place Subdivision

Final Plat recorded with the County

Performance Bond in place

Complete

West Linn High School

Parking Reconfiguration

Maintenance Bond in place through 02/03/2015 Complete