Rosemont Road Project Page

Rosemont Road improvements will take place during a two- to three-week project in the Summer of 2011.  This project page contains updates from this street project.

July 18, 2011 - Rosemont improvements project is started today. Estimated construction time is two- to three-weeks. Improvements consist of street widening to accommodate bike lane, curb with gutter and concrete sidewalk. A section of existing asphalt sidewalk (north side of Rosemont) will be temporary closed for pedestrian traffic from the south end of Miles Drive to the west end of Oppenlander Field (approximately 520 LF) .