Private Development Projects

Link to Private Development Permit Application

For more information about the projects listed below, please contact:

Private Development Program Manager at 503-722-5500

Project Details Current Status

Estimated Project

Completion Date

StoneKing Subdivision Public Improvement Engineering Plan Review and Construction Permit are under review June 2015
Lort Partition Public Improvement Engineering Plan and Construction Permit are under review June 2015
Shady Hollow Village Public Improvement Engineering Plan and Construction Permit under review March 2015
6th Ave Partition

Water line and pavement improvements complete

Curb and gutter installed

March 2015
Renaissance at Willamette

Substantially complete, Plat signed and recorded

Working on issuance of SDC credit

February 2015
Suncrest Partition

Curb and sidewalk installed

Sanitary sewer services connected

March 2015
Harper Subdivision

Public Improvement Engineering Plan Review and Construction Permit are approved

Grading and construction under way

April 2015
Weatherhill Subdivision

Construction is under way

Stormwater, sanitary sewer, and water main are installed

Curb and gutter are in place

May 2015

Lake Oswego Tigard Water Treatment Plant

Transmission Line

Public Improvement Engineering Review and Construction permit is complete

Onsite construction is under LOTWTP permit. 

2016

Lake Oswego-Tigard

Water Treatment Plant

Under Construction

 

Paving on Old River Rd. between Cedaroak and Kenthorpe is complete.

2016
     

 

Completed Projects

 
Rosemont Subdivision

Completed all Public Improvements

Plat approved and released to County

Complete
Sunbreak Subdivision

Completed all Public Improvements

Plat approved and released to County

Complete
Police Station New building is occupied and open to the public Complete
Benjamin Heights Partition

Final Plat has been approved and released to Clackamas County for recording

Complete
Santa Anita Partition

Completed all Public Improvements

Final Plat approved and released to Clackamas County

Complete
Dollar Street Partition

Final Plat recorded with the County

Complete
Falcon Place Subdivision

Final Plat recorded with the County

Performance Bond in place

Complete

West Linn High School

Parking Reconfiguration

Maintenance Bond in place through 02/03/2015 Complete