Project Details

Current Status

Estimated Project 
Completion Date

Bolton Reservoir Replacement Design

Reservoir Siting Analysis reviewed at 11/17/14 City Council Work Session

Geotechnical Report review underway

Spring 2015
Rosemont Reservoir Safety Improvements

Installation of carrier transfer switching stations has been completed

Electrical inspections to begin in late January

June 2015
Santa Anita and Rosemont Intersection

Funded by System Development Charges

Traffic signal is operational and was turned on 12/09/2014

Early 2015

Median Restoration Project

Phase 2 underway

Ultrablock retaining wall in place on Santa Anita between Horton and Pimlico. Plants have been removed and drainage system is in place

Late Fall 2014
Bland Rosemont Intertie Pump Station

Excavation for pump house began week of 07/14/2014. Reservoir tie in complete

Suction piping and pump cans set

December 2014
     
  Completed Projects  
Bland Rosemont Transmission Line Approximately 2,900 linear feet of 12-inch waterline was installed to connect the Bland and Rosemont pressure zones.  In addition, approximately 1,300 linear feet of sidewalk along the west side of Salamo was installed between Weatherhill and Bland. Completed
Mapleton Water Main Replacement Abandonment and replacement of approximately 4,000 linear feet of primarily 6-inch asbestos cement pipe with 8-inch ductile iron pipe was completed. Completed
Sanitary Sewer Rehab Stage 4 Approximately 18,000 linear feet of 8-inch diameter sanitary sewer with cured in place pipe was completed Completed
2014 Road Program Approximately 1,600 tons of asphalt, 700 ln-ft of storm drain improvements, and 4,000 sq. yd's of Slurry seal street improvements completed Completed
Concrete Streets Project

Approximately 7,000 sq. yd's of concrete street improvements completed

Completed
Chestnut and Skye Parkway Waterline Approximately 800 linear feet of 8-inch ductile iron water pipe was installed Completed
Evah Lane Waterline Approximately 400 linear feet of 8-inch ductile iron water pipe was installed Completed

LED Street Light

Conversion PGE

900 lights converted

City received reimbursement from Energy Trust of Oregon which was presented to Council in January 2014

Completed

West Linn Public

Library Parking Lot

Final light pole installation completed late January 2014

Completed

Road Program 2013 Maintenance Bond Secured Completed

 

Public Improvement Projects (City Projects)

Public Works Director
Phone: 503-722-5500
Fax: 503-656-4106
PUBLIC WORKS DEPARTMENT - ENGINEERING DIVISION

 

Also, use the "Projects" pull-down menu to view current and previous year projects for Streets, Water, Sanitary Sewer, and Stormwater.